One of the barges supporting the Gorgon LNG build from a speedboat after full lifting and lifted equipment inspections had been completed

LNG Inspection & Management

Vertech was contracted on short notice to bring all marine lifting equipment for 21 barges and six onshore LNG areas into compliance with Gorgon LNG. The scope included an initial audit, QA/QC, baseline inspection and surveys compiling all manufacturer certifications, and regular comprehensive equipment inspections.

Our Viiper system and site work was audited by Chevron numerous times and found to be 100% compliant.

Speak to Vertech Group about Your Next Project

"*" indicates required fields

This field is for validation purposes and should be left unchanged.
A vertech IRATA rope access technician is carrying out testing on marine lifting equipment located on an offshore barge.